Sneberger v. Morrison

by
Plaintiff entered into a verbal contract with Jerry Morrison for the construction of a log home on her property. Plaintiff entered into a second verbal contract with James Phillips to build the basement walls and a chimney with two fireplaces. Concerned about the number of apparent defects in the construction and excessive costs of the labor and materials, Plaintiff fired Morrison. Plaintiff later filed suit against Morrison and Phillips (together, Defendants), alleging fraud and misrepresentation, breach of contract, and negligence, among other claims. The jury returned a verdict in favor of Plaintiff only with respect to her negligence claim against Morrison. The jury further found that Plaintiff had failed to mitigate her damages and/or was comparatively negligent. The Supreme Court affirmed, holding that the trial court did not err in (1) limiting the time the parties had to present the case to the jury; (2) placing limitations on expert testimony; (3) granting judgment as a matter of law in favor of Phillips; (4) denying Plaintiff’s motion for judgment as a matter of law with respect to her negligence and breach of warranty claims against Morrison; (5) instructing the jury on comparative negligence; (6) instructing the jury on outrageous conduct; and (7) denying Plaintiff’s motion for a new trial. View "Sneberger v. Morrison" on Justia Law